mp-nursing-college-diverts-it-park-space:cag-report-says-minior-mineral-corporation-paid-₹2.5-crore-to-contractors-in-alleged-multi-layered-scam

The Comptroller and Auditor General of India (CAG) has found several irregularities in two government departments in Madhya Pradesh. In its new report, the CAG says that the Madhya Pradesh State Electronics Development Corporation Limited gave plots and spaces to different institutions in IT parks but did not check how they were being used. Because of this, one institution that should have run a call centre was instead operating a nursing college. The report also says that Madhya Pradesh Laghu Udyog Nigam Limited released ₹2.79 crore to contractors without taking the required royalty documents. As per rules, the department should have collected ‘No Dues Certificates’ before making payments. The CAG report covers the working of state public sector enterprises for the financial year ending 31 March 2023. It also includes details about renewable energy projects and financial problems in power distribution companies. The report gives several recommendations to the state government. Long Term Strategy Not Prepared
CAG found that MP State Electronic Development Corporation (MPSEDC) did not prepare any long-term strategy for IT parks. Due to this, no target was set for the institutions that were allotted land or space in the IT park. As a result, the four IT parks in Bhopal, Indore (Sihansa and Pardeshipura), Jabalpur, and Gwalior did not see uniform development. If the development of plots in Gwalior did not start, then commercial activity could only begin on some of the plots allotted in the other three locations. Only 4% employment from IT Park
CAG has stated in its report that the government has completely failed to increase employment opportunities through the IT Park. According to the land provided by the government for the IT Park, 15,000 people were supposed to get employment, but only 576 received it. Furthermore, several shortcomings were found in the plot allotment process. The report stated that it indicates a lack of effort on the part of the department to actively allot plots to start business activities. Excluding these 19 plots, regarding the 240 plots actually allotted, the employment generation target was 14,548, against which 576, or 3.96 percent, was achieved. The notable point is that regarding 123 out of 240 plots, the allotment period has exceeded 3 years, but production has not started. Encroachment on 13.57 acres of land in Bhopal-Indore IT Park
The report revealed that 13.57 acres of land in the IT Parks of Bhopal and Indore have been encroached upon. This resulted in a revenue loss of 2.28 crore rupees for the government. In addition, the government also incurred a loss of 3.62 crore rupees spent on developing this land. When CAG inquired about efforts to remove the encroachment, the corporation did not provide any response. Development fees not changed for 10 years
MPSEDC did not make any changes to the development fees for 10 years (2013 to 2023). While the corporation was capable of revising it from time to time. In such a situation, only Rs 42.86 crore was recovered as development fees at the 10-year-old rate. Whereas the development expenditure was Rs 228.10 crore. Land given to non-IT companies
Out of 20 units in IT parks in Bhopal, Indore, and Jabalpur, 11 do not fall under the IT sector category. Far from taking any action against these firms, the corporation provided them with a land subsidy of Rs 4 crore and an incentive amount of approximately Rs 61 lakh. According to the report, a firm named M/s Saffron Solar System, located in Jabalpur IT Park, was allotted 2926 acres of land in 2926. As per its agreement, the firm was supposed to manufacture PV solar panels and modules. When the firm did not start work here for three years, the land allotment was cancelled in 2022. However, upon submission of some documents and a list of machinery, the land was returned to the firm. The notable thing is that the list of equipment presented by the firm included soldering iron, drill, cutters, and a weighing machine. Whereas these equipments are not even used in the manufacturing of PV solar panels and modules. The corporation had also given a subsidy of 60.73 lakh to this firm. Similarly, in Bhopal, M/s Green Surfer was supposed to manufacture LED lights electronic products in 2028, but investigation revealed that only bulb parts were stocked here. This firm had also taken a subsidy of 1.64 crore from the government. 36 Crores not recovered from Rewa Ultra mega solar limited
Similarly, CAG also found negligence in the New and Renewable Energy Development Corporation. According to the report, the corporation had entered into a land use permission agreement with Rewa Ultra Mega Solar Limited in April 2017 for the Rewa Solar Park. The corporation required land use fees in five equal annual installments starting from April 2017. The corporation neither raised the demand nor recovered it on time. The corporation also did not levy an interest charge of Rs 8.6 crore for delayed payments under government orders. Similarly, in the case of solar park projects, the corporation could not recover land use fees of Rs 25.12 crore from the company till March 2023, nor was an interest of Rs 2.65 crore levied for delays in land use fee payments. Contract awarded to a blacklisted company
The West Zone Power Distribution Company awarded the line maintenance work to a tainted contractor. According to the report, as per the terms and conditions of the contract, the company had to ensure the technical and financial capability of the bidder. It also had to be checked whether any lawsuit was pending against the bidder. In March 2017, the contract was awarded to the joint company of M/s Mohammad Arif Sheikh and M/s S Hifazat Ali. CAG, upon evaluating the technical commercial bid, found that the contractor had stated in the bid application that there was no lawsuit against their company. Whereas, the contractor had provided information about three previous lawsuits while bidding for an agreement under the DG KY scheme in August 2016. These lawsuits were related to Madhya Pradesh Housing and Infrastructure Development Board, Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Indore, and TWD Barwani.